Federal report scolds DTE for errors before Fermi 2 pump break

Published On: Jan 30 2013 04:44:34 PM EST
Updated On: Jan 30 2013 04:45:04 PM EST
Fermi 2
FRENCHTOWN TOWNSHIP, Mich. -

A federal report is criticizing DTE Energy Co. for what it says are maintenance failures leading up to the June breakdown of a cooling water pump at the Fermi 2 nuclear power plant.

Read: Fermi 2 plant restarts at low power.

The Nuclear Regulatory Commission's report says DTE failed to adequately oversee an earlier overhaul of the giant pump. The plant is in Monroe County's Frenchtown Township, near Monroe.

The Monroe Evening News says the failure of the south reactor pump has limited plant power to 68 percent.

Watch: Fermi 2 employee accused of drinking during shift

DTE says it expects to fix the pump during the first half of 2013.

The NRC's report says the failure resulted from improper reassembly after maintenance, inadequate maintenance testing, and restarting the pump out of normal startup sequence.

DTE says it agrees with the report and has made corrections.

Comments

The views expressed below are not those of Click On Detroit, WDIV, or its affiliated companies. By clicking on "Post," you acknowledge that you have read the Terms of Service and your comment is in compliance with such terms. Readers, please help keep this discussion respectful and on topic by flagging comments that are offensive or inappropriate (hover over the commenter's name and you'll see the flag option appear on right side of that line). And remember, respect goes both ways: Tolerance of others' opinions is important in a free discourse. If you're easily offended by strong opinions, you might skip reading comments entirely.